Leverer Plan for Utbygging og Drift (PUD) for Skogul

Aker BP ASA leverer Plan for Utbygging og Drift (PUD) for Skogul-prosjektet (tidligere Storklakken) til Olje- og energidepartementet, på vegne av lisenspartnerskapet.

Pressemelding om PUD for Skogul er kun på engelsk:

The Skogul field is located 30 kilometers north of Alvheim FPSO, and will be developed as a subsea tieback to Alvheim via Vilje.

Recoverable reserves are estimated to around 10 million barrels of oil equivalents. Total investments are estimated to NOK 1.5 billion in real terms, and production start is planned for first quarter 2020.

The production well at Skogul will be subsea production well number 35 in the Alvheim area, and represents Aker BP’s continuous effort to maximize value and extend economical field life to the benefit of the company and its partners.

Joint venture partners in Skogul are Aker BP ASA (operator 65%) and PGNiG Upstream Norway AS (35%).

PS: In November 2017, the Ministry of Petroleum and Energy approved new name for Skogul (formerly Storklakken)